NPS Welcomes New Bus Barn- progress

November 18, 2020

August 21

Successful work completed this week:

  • Water and Sanitary sewer was brought within 5’ of the building
  • Storm sewer system including drops for the downspouts was installed
  • Pipe and fittings for plumbing underground were delivered

 

September 4

Successful work completed this week:

  • Electricians finished grounding for the building
  • Plumbers continued underground and started setting trench drains

September 11

Successful work completed this week:

  • Trench drain installation was completed
  • Interceptors were installed

 

 

September 18

Successful work completed this week:

  • Trenched 2 conduits for power to school sign on hwy 12
  • Trenched in 2” conduit for propane line
  • Started pouring building slab
  • Started prepping for sidewalk and flume along existing school  

October 2

Successful work completed this week:

  • Finished pouring the sidewalk along the gym
  • Started working on the curb inlets
  • Started steel erection

 

October 9

Successful work completed this week:

  • Finished sheeting the exterior walls
  • Pulled banding and started stretching simple saver
  • Started insulating and sheeting the roof
  • Formed and poured the curb inlet walls
  • Staked out curb and gutter and light pole locations

 

October 16

Successful work completed this week:

  • Finished insulating and sheeting the roof and installing ridge cap and trims
  • Set the curb inlet tops
  • Backfilled along the flume and removed the excess dirt from site
  • Moved LP tank to prep for slab
  • Started prepping for parking lot and curb and gutter

 

 

October 23

Successful work completed this week:

  • Steel erection was completed
  • Holes for light poles were drilled and tied together
  • Started grading for parking lot curb and gutter
  • Drilled holes for bollards
  • Started setting forms for the apron
  • Poured the pad for the propane tank
  • Moved job trailer and excess material off site for paving

 

October 30

Successful work completed this week:

  • Set all the bollards
  • Set propane tank
  • Started pouring aprons
  • Poured north curb and gutter
  • Poured South curb and gutter
  • Electricians poured light poles
  • We continued grading for the parking lot

 

November 6

Successful work completed this week:

  • Installed erosion control mats and seeded black dirt with grass seed
  • Continued exterior paving
  • Continued final grading of parking lot and driveway

 

 

November 13

 

Successful work completed this week:

  • Poured the last strip of the parking lot
  • Formed and poured the remaining curb and gutter