Bus Barn update

February 19, 2021

Bus Project Progression (2).pdf

 

Bus Barn Project Progression

August 21

Successful work completed this week:

  • Water and Sanitary sewer were brought within 5’ of building
  • Storm sewer system including drops for the downspouts was installed
  • Pipe and fittings for plumbing underground were delivered

 

 

September 4

Successful work completed this week:

  • Electricians finished grounding for the building
  • Plumbers continued underground and started setting trench drains

September 11

Successful work completed this week:

  • Trench drain installation was completed
  • Interceptors were installed

 

 

September 18

Successful work completed this week:

  • Trenched 2 conduits for power to school sign on hwy 12
  • Trenched in 2” conduit for propane line
  • Started pouring building slab
  • Started prepping for sidewalk and flume along existing school  

October 2

Successful work completed this week:

  • Finished pouring the sidewalk along the gym
  • Started working on the curb inlets
  • Started steel erection

 

October 9

Successful work completed this week:

  • Finished sheeting the exterior walls
  • Pulled banding and started stretching simple saver
  • Started insulating and sheeting the roof
  • Formed and poured the curb inlet walls
  • Staked out curb and gutter and light pole locations

 

October 16

Successful work completed this week:

  • Finished insulating and sheeting the roof and installing ridge cap and trims
  • Set the curb inlet tops
  • Backfilled along the flume and removed the excess dirt from site
  • Moved LP tank to prep for slab
  • Started prepping for parking lot and curb and gutter

 

 

October 23

Successful work completed this week:

  • Steel erection was completed
  • Holes for light poles were drilled and tied together
  • Started grading for parking lot curb and gutter
  • Drilled holes for bollards
  • Started setting forms for the apron
  • Poured the pad for the propane tank
  • Moved job trailer and excess material off site for paving

 

October 30

Successful work completed this week:

  • Set all the bollards
  • Set propane tank
  • Started pouring aprons
  • Poured north curb and gutter
  • Poured South curb and gutter
  • Electricians poured light poles
  • We continued grading for the parking lot

 

November 6

Successful work completed this week:

  • Installed erosion control mats and seeded black dirt with grass seed
  • Continued exterior paving
  • Continued final grading of parking lot and driveway

 

 

November 13

 

Successful work completed this week:

  • Poured the last strip of the parking lot
  • Formed and poured the remaining curb and gutter

 

November 20, 2020

Successful work completed this week:

  • Finished pouring the parking lot
  • Graded and poured the driveway, apron and remaining curbs

 

Successful work completed this week:

  • Formed and poured street panels and sidewalk
  • Shut down the street and access to site

 

 

 

 

December 4, 2020

Successful work completed this week:

  • Started installing the garage doors
  • Hung temporary lights
  • Pulled temp power to the building
  • Started running conduit for the lights
  • Steel studs for interior framing were delivered

 


December 11, 2020

 

Successful work completed this week:

  • Sealed all control joints in the parking lot
  • Completed all interior framing
  • Continued working on the OHDs
  • Built chain link fence enclosure around the propane tank
  • Electricians continued running conduit and mounting boxes
  • Finished final grade and clean up of site
  • Seeded grass and placed erosion control mats
  • Interior door frames and slabs were delivered

 

December 18, 2020

Successful work completed this week:

  • HVAC contractor hung radiant tube heaters, fans and started running vent piping
  • Electricians hung plywood for panel, mounted panel and continued on their scope
  • TSI painted parking lot markings
  • Delivery of wash bay PVC liner panel

 

 

December 24, 2020

Successful work completed this week:

  • Carlson Co-op Ran gas line to the building and set the regulator
  • C.W. Suter Started running gas lines to the heaters
  • C.W. Suter started running air lines, Water lines and roughed in the bathroom and mechanical room
  • Interior hollow metal door frames were installed
  • Electricians continued running conduit and working on their scope
  • OHDs were completed

 

January 1, 2021

Successful work completed this week:

  • Electricians measured distance to transformer for wire and continued their scope
  • Plumbers finished the gas line to all the heaters and continued their scope
  • Carlsons Co-op turned on LP service to the building

             

January 8, 2021

Successful work completed this week:

  • Fired up two heaters for temporary heat inside the building
  • C.W. Suter finished mechanical rough in
  • Electricians continued running conduit and started pulling wire  
  • Installed plywood decking above office bathroom and mech room
  • Started installing plywood in the wash bay

 

January 15, 2021

Successful work completed this week:

  • Menford pulled power to the building
  • NuAge finished hanging plywood in the wash bay
  • C.W. Suter stubbed sewer vent pipe out of the roof
  • C.W. Suter ran regulator vents outside
  • C.W. Suter Insulated water lines
  • Menford continued running conduit

 

January 22, 2021

Successful work completed this week:

  • Menford Electric finished running conduit and started pulling wire
  • Installed signage on the front of the building
  • Insulated parting walls and rooms
  • Started hanging plywood in the south bay
  • Hung sheetrock in the office, bathroom, mechanical room, and parting wall
  • Started hanging interior lights

 

  

January 29, 2021

Successful work completed this week:

  • Hung all the PVC liner in the wash bay
  • Started taping drywall
  • Continued hanging plywood in the south bay
  • Electricians continued on their scope
  • Pulled fiber line down to the school

      

 

Successful work completed this week:

  • New breaker was installed, and power turned on in the building
  • Midwest alarm installed security system
  • Menford installed exterior building lights and continued their scope
  • Menford started hanging interior lights
  • NuAge finished plywood in the south bay
  • Nuage caulked interior slab saw cuts

 

February 12, 2021

Successful work completed this week:

  • Pain

    Bus Barn Project Progression

    August 21

    Successful work completed this week:

  • Water and Sanitary sewer were brought within 5’ of building
  • Storm sewer system including drops for the downspouts was installed
  • Pipe and fittings for plumbing underground were delivered
  •  

    September 4

    Successful work completed this week:

  • Electricians finished grounding for the building
  • Plumbers continued underground and started setting trench drains
  • September 11

    Successful work completed this week:

  • Trench drain installation was completed
  • Interceptors were installed
  •  

     

    September 18

    Successful work completed this week:

  • Trenched 2 conduits for power to school sign on hwy 12
  • Trenched in 2” conduit for propane line
  • Started pouring building slab
  • Started prepping for sidewalk and flume along existing school  
  • October 2

    Successful work completed this week:

  • Finished pouring the sidewalk along the gym
  • Started working on the curb inlets
  • Started steel erection
  •  

    October 9

    Successful work completed this week:

  • Finished sheeting the exterior walls
  • Pulled banding and started stretching simple saver
  • Started insulating and sheeting the roof
  • Formed and poured the curb inlet walls
  • Staked out curb and gutter and light pole locations
  •  

    October 16

    Successful work completed this week:

  • Finished insulating and sheeting the roof and installing ridge cap and trims
  • Set the curb inlet tops
  • Backfilled along the flume and removed the excess dirt from site
  • Moved LP tank to prep for slab
  • Started prepping for parking lot and curb and gutter
  •  

     

    October 23

    Successful work completed this week:

  • Steel erection was completed
  • Holes for light poles were drilled and tied together
  • Started grading for parking lot curb and gutter
  • Drilled holes for bollards
  • Started setting forms for the apron
  • Poured the pad for the propane tank
  • Moved job trailer and excess material off site for paving
  •  

    October 30

    Successful work completed this week:

  • Set all the bollards
  • Set propane tank
  • Started pouring aprons
  • Poured north curb and gutter
  • Poured South curb and gutter
  • Electricians poured light poles
  • We continued grading for the parking lot
  •  

    November 6

    Successful work completed this week:

  • Installed erosion control mats and seeded black dirt with grass seed
  • Continued exterior paving
  • Continued final grading of parking lot and driveway
  •  

     

    November 13

     

    Successful work completed this week:

  • Poured the last strip of the parking lot
  • Formed and poured the remaining curb and gutter
  •  

    November 20, 2020

    Successful work completed this week:

  • Finished pouring the parking lot
  • Graded and poured the driveway, apron and remaining curbs
  •  

    Successful work completed this week:

  • Formed and poured street panels and sidewalk
  • Shut down the street and access to site
  •  

     

     

     

    December 4, 2020

    Successful work completed this week:

  • Started installing the garage doors
  • Hung temporary lights
  • Pulled temp power to the building
  • Started running conduit for the lights
  • Steel studs for interior framing were delivered
  •  


    December 11, 2020

     

    Successful work completed this week:

  • Sealed all control joints in the parking lot
  • Completed all interior framing
  • Continued working on the OHDs
  • Built chain link fence enclosure around the propane tank
  • Electricians continued running conduit and mounting boxes
  • Finished final grade and clean up of site
  • Seeded grass and placed erosion control mats
  • Interior door frames and slabs were delivered
  •  

    December 18, 2020

    Successful work completed this week:

  • HVAC contractor hung radiant tube heaters, fans and started running vent piping
  • Electricians hung plywood for panel, mounted panel and continued on their scope
  • TSI painted parking lot markings
  • Delivery of wash bay PVC liner panel
  •  

     

    December 24, 2020

    Successful work completed this week:

  • Carlson Co-op Ran gas line to the building and set the regulator
  • C.W. Suter Started running gas lines to the heaters
  • C.W. Suter started running air lines, Water lines and roughed in the bathroom and mechanical room
  • Interior hollow metal door frames were installed
  • Electricians continued running conduit and working on their scope
  • OHDs were completed
  •  

    January 1, 2021

    Successful work completed this week:

  • Electricians measured distance to transformer for wire and continued their scope
  • Plumbers finished the gas line to all the heaters and continued their scope
  • Carlsons Co-op turned on LP service to the building
  •              

    January 8, 2021

    Successful work completed this week:

  • Fired up two heaters for temporary heat inside the building
  • C.W. Suter finished mechanical rough in
  • Electricians continued running conduit and started pulling wire  
  • Installed plywood decking above office bathroom and mech room
  • Started installing plywood in the wash bay
  •  

    January 15, 2021

    Successful work completed this week:

  • Menford pulled power to the building
  • NuAge finished hanging plywood in the wash bay
  • C.W. Suter stubbed sewer vent pipe out of the roof
  • C.W. Suter ran regulator vents outside
  • C.W. Suter Insulated water lines
  • Menford continued running conduit
  •  

    January 22, 2021

    Successful work completed this week:

  • Menford Electric finished running conduit and started pulling wire
  • Installed signage on the front of the building
  • Insulated parting walls and rooms
  • Started hanging plywood in the south bay
  • Hung sheetrock in the office, bathroom, mechanical room, and parting wall
  • Started hanging interior lights
  •  

      

    January 29, 2021

    Successful work completed this week:

  • Hung all the PVC liner in the wash bay
  • Started taping drywall
  • Continued hanging plywood in the south bay
  • Electricians continued on their scope
  • Pulled fiber line down to the school
  •       

     

    Successful work completed this week:

  • New breaker was installed, and power turned on in the building
  • Midwest alarm installed security system
  • Menford installed exterior building lights and continued their scope
  • Menford started hanging interior lights
  • NuAge finished plywood in the south bay
  • Nuage caulked interior slab saw cuts
  •  

    February 12, 2021

    Successful work completed this week:

  • Painters painted all the drywall, plywood, doors, and frames (OHD in wash bay)
  • Electricians continued their scope
  • Water softener was delivered
  • C W Suter finished venting heaters and started installing dampeners
  • Ceiling grid was installed
  •  

     

    February 19, 2021

    Successful work completed this week:

  • Surface Sealers completed Tnemec Deco tread epoxy flooring in the wash bay and bathroom
  • CW Suter started setting equipment in mechanical room
  • Menford Electric hung lights in the south bay and continued on their scope
  • Data Cabinet was installed
  • Upper Midwest started Setting limits on OHDS
  • ters painted all the drywall, plywood, doors, and frames (OHD in wash bay)
  • Electricians continued their scope
  • Water softener was delivered
  • C W Suter finished venting heaters and started installing dampeners
  • Ceiling grid was installed

 

 

February 19, 2021

Successful work completed this week:

  • Surface Sealers completed Tnemec Deco tread epoxy flooring in the wash bay and bathroom
  • CW Suter started setting equipment in mechanical room
  • Menford Electric hung lights in the south bay and continued on their scope
  • Data Cabinet was installed
  • Upper Midwest started Setting limits on OHDS